Maerskdrilling.com uses cookies for the purposes of statistical analysis, targeted marketing of our products, improving the friendliness and usability of our website, tailoring content to your interests and engaging with social media. By visiting our website, you consent to our and third party use of cookies as described in our privacy and cookie policy.

Voyager: Completing 200 days ahead of schedule in Ghana

In approximately 15 months the Voyager was able to drill fifteen new wells, re-enter three wells, drill four sidetrack sections and run lower completion on nine wells.

Voyager: Completing 200 days ahead of schedule in Ghana

Expected time saving to the project was approximately 200 days. The additional work done during the pre-drilling phase, while preparing the rig for the completion operations, was key to keep the well operations performance at same level of excellence and improve during the wells completion incoming project phase.

Read more

Maersk Explorer 1 (1).jpg
Implementing self-verification onboard Maersk Explorer
JMI 5287.jpg
Integrator: Increasing energy efficiency
Venturer-nosmoke.jpg
Venturer: Spudding the world's deepest well in strong currents
Viking.jpg
Viking: Extended flow back operations in the US Gulf of Mexico
Intrepid 5.jpg
Intrepid: Hi-tech rig on Martin Linge field