Maerskdrilling.com uses cookies for the purposes of statistical analysis, targeted marketing of our products, improving the friendliness and usability of our website, tailoring content to your interests and engaging with social media. By visiting our website, you consent to our and third party use of cookies as described in our privacy and cookie policy.

Voyager: Completing 200 days ahead of schedule in Ghana

In approximately 15 months the Voyager was able to drill fifteen new wells, re-enter three wells, drill four sidetrack sections and run lower completion on nine wells.

Voyager: Completing 200 days ahead of schedule in Ghana

Expected time saving to the project was approximately 200 days. The additional work done during the pre-drilling phase, while preparing the rig for the completion operations, was key to keep the well operations performance at same level of excellence and improve during the wells completion incoming project phase.

Read more

IMG_0021.jpg
Explorer: A good year in Shah Deniz
Interceptor xx.jpg
Interceptor setting a Norwegian record by drilling more than a mile in one day
100-0004 IMG.jpg
Drilling the undrillable
Maersk Discoverer  0195 (1).png
Discoverer Drilling HPHT wells offshore Egypt
1520-0090.jpg
Reacher: Successfully abandoning wells offshore Norway