Resilient setting new benchmarks for completing workovers

Performing workovers for Total offshore Denmark, Maersk Resilient saved our customer both time and costs by introducing improved procedures supporting various parts of the operation.

Resilient setting new benchmarks for completing workovers

By changing the procedures, the total time for rigging up and pressure testing the coil tubing equipment was decreased by more than 50%. The Maersk Resilient team also
introduced a new, safer and faster procedure for handling the surface Xmas trees, by utilising the X-Y cantilever’s ability to skid while being attached to the Xmas tree.

These achievements were highly praised by customer Total, who expressed that the team had set new benchmarks for the completion of workover programme.

Read more

AJ7P2089 (3).png
Upgraded for MPD excellence
FULL Maerskdrilling Maerskinvincible 091019 7158
Record for Maersk Invincible: 2278m drilled in one day
Maersk19
What we’ve learnt from the COVID-19 pandemic so far
Resolute.jpg (1)
Moving the SPS to a virtual space
Maersk INFOGRAPHIC Corona Final AIRBRIDGE
The Maersk Bridge