Resilient setting new benchmarks for completing workovers

Performing workovers for Total offshore Denmark, Maersk Resilient saved our customer both time and costs by introducing improved procedures supporting various parts of the operation.

Resilient setting new benchmarks for completing workovers

By changing the procedures, the total time for rigging up and pressure testing the coil tubing equipment was decreased by more than 50%. The Maersk Resilient team also
introduced a new, safer and faster procedure for handling the surface Xmas trees, by utilising the X-Y cantilever’s ability to skid while being attached to the Xmas tree.

These achievements were highly praised by customer Total, who expressed that the team had set new benchmarks for the completion of workover programme.

Read more

Voyager-44.jpg
Equatorial Guinea - creating long-term value on a short-term contract
Voyager.jpg
First successful delivery of virtual DWOP to Total Angola
HSE_Banner2.png
Maersk Drilling sees best safety statistics in five years
Intrepid 222 (2)
Maersk Drilling COVID-19 Task Force takes proactive approach and leverages key learnings
AJ7P2089 (3).png
Upgraded for MPD excellence