Intrepid: Maximising performance in Norway

In June 2018, operator AkerBP was in a need of a rig to perform an appraisal of the Hanz field. At that time, Maersk Intrepid
was assigned to Equinor at the Martin Linge field.

Intrepid: Maximising performance in Norway

Within only three weeks, a sublet between the parties was agreed – the rig was moved from Martin Linge to Hanz, and spud was done.

Intrepid’s time at Hanz included a record of 414 “dry hole days”. Such a performance was made possible by the rig’s ability to drill 1,500m in 12¼” section and 1,300m in 8½” section within 24 hours. Intrepid’s offline capacity maximised the performance, resulting in casing and trip speed exceeding all expectations.

Read more

AJ7P2089 (3).png
Upgraded for MPD excellence
FULL Maerskdrilling Maerskinvincible 091019 7158
Record for Maersk Invincible: 2278m drilled in one day
Maersk19
What we’ve learnt from the COVID-19 pandemic so far
Resolute.jpg (1)
Moving the SPS to a virtual space
Maersk INFOGRAPHIC Corona Final AIRBRIDGE
The Maersk Bridge