Developer: Successful reactivation in Colombia

Prior to entering Colombia for the first time, the semi-submersible Mærsk Developer was reactivated from warm stacking to drill one well for Repsol.

Developer: Successful reactivation in Colombia

The reactivation of the rig, including full manning, was completed in only eight weeks – commencing operations mid-April 2017. The reactivated rig finished Maersk Drilling’s first operation in Colombia 9.5% faster than projected, with an operational uptime of 99.3%.